The Oil fired Combi is now in it's new position so we began plumbing it in. All the new pipework was fabricated and fastened up in the roofspace. We did forget to tee in the hot water to upstairs but that's a 5 minute job to sort it out. We also had one of the 'push fit' connectors come apart ( i didn't push it in far enough) Fortunately i was next to the stop tap so nothing a few towels couldn't handle.
The heating side still needs work plus the under floor heating ststem needs sorting then the oil side needs commisioning. But there is light and heat at the end of the tunnel.
At the Paying' job tomorrow so no more progress till sunday.