Looping the loops
A really good day today!!
The conservatory roof is now 2/3rds tiled, the 2 velux windows have had all the flashings fitted and so now should be watertight, just 2 rows of tiles to be fitted and the lead flashings under the house windows.
The lead valley has been created and the first piece of Georgian Wired Glass fitted.
Then we moved inside as the light faded to lay the pipework for the underfloor heating.
Tomorrow we have to pressurize the pipework and then put down the 'Scree' to cover the pipes.
I should be on nights tonight but we finished late and there was loads of tidying up to do so i'm not. Just one day's leave left now!