Unit EC 20 is starting up again after it tripped yesterday evening (the safetysystem was activated when a parameter was reached in the balance of the fluegas/condensatepre-heater).
But: the tests have to go on so we are starting up again.
That is done in the local control room (see yesterday's Blip), but we can watch the plant from the Central Control Room.
And: we can support and assist when necessary...
In the middle you can see the joysticksystem which allows us to control the camera's.
On the mimic panel you can see the complete process, consisting of the boiler (two-flow Benson boiler), gasturbine (GTC) and steamturbine, consisting of one HP, one MP and two low pressure turbines.