Due to a problem at our unit in Nijmegen we had to start up all available units.
There had been an explosion at unit G13 at Nijmegen; apparently it was assumed as a problem around the feedwatertank but now it looks like a torn off high pressure steampipe the boilerpressure came down from 180 bar ( 2 610.679 284 1 pound/square inch ) to 4 bar (58.015 095 203 psi ) in about 10 minutes. At our plotting screens we can see what happens in the systems over there)