I went to the house to measure partition widths and some of the smaller details of the bathroom and shower room for Tivoli, who, far more expert than I am is very kindly doing my tiling design.
The larger-than-expected ducting spills into what was going to be bathroom space at floor level (this shows how it spills into ceiling space - and the ceilings will be lowered) and even with the help of the site foreman I couldn't work out how the boxing is going to work. He told me the architect had done new drawings but I couldn't unravel them so I sent them direct to Tivoli.
He also told me the bath will be needed next week so I did a task much more within my capacity: walked to the bathroom place I went into four days ago and ordered it. They will let me know when it arrives and will deliver it whenever the builders call them. Simple.