One I prepared earlier.......

This is one of the boxes I Blipped yesterday installed in the boat park.
In January contractors dug the trench and installed the heavy cable and fitted the 12 posts.
In early March I terminated the cables in the lower boxes (it was bruddy cold and the cables were very stiff) and moved one old box from the old supply to the new.
A fortnight ago we did some work on the club distribution system and moved two more old boxes onto the new system.
Today we moved another 4 plus fitted two of the new boxes.
The old system is now disconnected and we have three new boxes to finish the job completely - probably in about three weeks time.
It has been a bit of a saga.