Borwin-Alpha

Was finally lifted off the barge and put on top of her jacket this afternoon. You see the two tiny people underneath the module? The module's weight is almost 3200 tons, so with a capacity of 7100 tons of the starboard crane alone, this was a piece of cake for her. Not true; every lift is regarded with the same professionalism and care as every other one. After some eighty windmills are installed here and all the cords are plugged into this converter station, 375.000 households in the northern part of Germany will get their energy from this windmill park. Eight hours welding en 12 hours job completion are left before we will leave to our next assignment. This time a three legged jacket in the Danish sector.