Blip #365
Took me almost two years. It proves that I am more or less half a year at home and the other half at sea. Pile driving is ready and now the subsea connection between piles and jackets must be made. It is done by grouting, pouring cement between the jacket pile guides and the piles. It will harden under water. Then the next step will be to take a level. All the eight legs (with the rusty caps on top) have to be cutted to an exact level. This is needed to put the topside on top. To be continued.