At unit EC 20: Some piping that lead from the boiler drainsystem back to the condenser and feedwatertank.
In this way we re-use the water which is drained during startup of the unit.
Some parts of the boiler need a minimum waterflow (just to cool the pipes) during startup.
At the left: a green vessel containing compressed air, for instrument air and to drive pneumatic tools (grinders and so on).
In the background: an emergency diesel driving a generator.
This is used when we have a total black out (which does not happen too often....)
Here in LARGE....
Today again a day in which we determined what to keep and store in the right way and what we had to throw away (and we throwed away a container full of unrecognizable things) :-)